The District of Barranquilla has historically had a major problem caused by the streams that run through its urban fabric, leading to stormwater runoff in the area, causing flooding, damage to urban infrastructure and service networks
Cost: 10.000.000,00 €
GOALS
The projected works are aimed at channeling the stream that runs along Calle 84, between Carreras 41B and 74, through the execution of a large buried collector, dimensioned for a return period of 100 years, with multicellular sections and an approximate length of 1,900 meters
Extras
- Severe floods that even caused deaths
- Large buried water collector, dimensioned for a period of 100 years
- Multicellular sections and length of 1,900 m